We have now taken handover of the office areas of Sheaf level 2 following some additional work to parts of the ceiling. The remainder of this level, including the SCALE UP room and IT suite, will be handed back to us towards the end of April and fit-out work is continuing in these areas to … Continue reading Sheaf/EMB update: 6 April 2016
Sheaf/EMB update: 23 March 2016
Overall the STEM project continues to progress well and we are on track according to the current programme. We will take handover of the office areas of Sheaf level 2 next Thursday (31 Mar). Although this is around a week later than planned, there was always some flexibility in this date and we decided to … Continue reading Sheaf/EMB update: 23 March 2016
Sheaf/EMB update: 9 March 2016
Work has begun this week on demolishing the stairs on level 2 of EMB. Due to the unavoidable level of noise disruption this will cause, work will not begin until around 5.30pm-6.00pm each day and will continue until around 2.00am. There will still be some noise in this area during the day as contractors remove … Continue reading Sheaf/EMB update: 9 March 2016
Sheaf/EMB update: 24 February 2016
The removal of the concrete steps between Sheaf and EMB has now been completed. Although every effort was made to mitigate the disturbance this caused, including providing quiet areas and limiting the hours of work, this has been a very disruptive part of the project. Thank you to all staff and students for their patience during … Continue reading Sheaf/EMB update: 24 February 2016
Sheaf/EMB update: 10 February 2016
Demolition of the concrete steps in the concourse area between Sheaf and EMB buildings began last week and is due to be completed by next Friday (19 February). Although every effort has been made to mitigate disturbance while this work is carried out, and to complete the most disruptive elements of this work out of … Continue reading Sheaf/EMB update: 10 February 2016
Sheaf/EMB update: 27 January 2016
All staff have decanted from Sheaf level 2 and EMB level 2 and both floors are under the control of the contractor. On Sheaf 2 plastering of the new walls is complete, ready for joinery and decoration to begin. In EMB 2 work is ongoing to remove ceilings and floors, and to isolate and strip … Continue reading Sheaf/EMB update: 27 January 2016
Sheaf/EMB update: 13 January 2016
The refurbishment of those areas of Sheaf level 3 which was planned as part of phase one of the STEM project has been successfully completed. The whole floor was handed back to the University last week, and we have now taken back responsibility for ongoing maintenance, cleaning and security of this level. Staff have begun to … Continue reading Sheaf/EMB update: 13 January 2016
Sheaf/EMB update: 14 December 2015
Phase 1 of the STEM project is nearing completion, and level 3 of Sheaf will be handed back to the University before Christmas. Work is ongoing on level 2; walls and ceilings continue to be stripped out and new walls will start being erected before Christmas. On Sheaf level 1, the work to remodel the … Continue reading Sheaf/EMB update: 14 December 2015
Sheaf/EMB update: 30 Nov 2015
Work on the Sheaf and Eric Mensforth (EMB) buildings is progressing well. Level 3 of Sheaf is nearing completion. Ceiling and other installation work is being completed in the next couple of weeks, and new flooring is being laid and rooms prepared for redecoration. Our planned handover date for level 3 is 22 December and … Continue reading Sheaf/EMB update: 30 Nov 2015
STEM update – 16 November 2015
Staff have now decanted from Sheaf level 2 and this has been handed over to the construction team to begin work this week. This means that work will now be taking place immediately above the level 1 helpdesk and the atrium. We are working with the contractors to minimise disruption to staff and students in … Continue reading STEM update – 16 November 2015