Progress on the STEM development is continuing well. Much of the heaviest work within the new atrium has been completed, and we’re now in a position to begin installing the wooden wall cladding and decorating. There are a few final pieces of disruptive work to complete in the next week or two that staff should … Continue reading Sheaf/EMB update: 8 February 2017
Sheaf/EMB update – 25 January 2017
Construction noise from the STEM development should reduce significantly from now on as the project nears its close, although staff and students should still expect intermittent disruption right through until completion in the spring. Activities which may cause some disturbance in the next couple of weeks are the creation of the new entrance into the … Continue reading Sheaf/EMB update – 25 January 2017
Sheaf/EMB update: 11 January 2017
Welcome to the first Sheaf/EMB update of 2017; what will be a busy and exciting year for STEM as we head towards the end of the project and the opening of our fantastic new space. There were no issues on site while the University was closed. Contractor Houltons is now back on site as planned … Continue reading Sheaf/EMB update: 11 January 2017
Sheaf/EMB update: 14 December 2016
Work on Sheaf and EMB, and the new atrium, continues to progress really well. The new chemical engineering lab, Sheaf 4014, is likely to be completed slightly ahead of schedule and rooms 3006, 3007 and 3009 in EMB may also be handed over to us before Christmas rather than in the new year. We have … Continue reading Sheaf/EMB update: 14 December 2016
Sheaf/EMB update: 30 November 2016
The pouring of screed for the new atrium floor began last week and so far has progressed very well. A levelling off layer has been put down in the main atrium area, and underfloor heating will be installed above this. A second layer of screed will be poured to seal this in and create the … Continue reading Sheaf/EMB update: 30 November 2016
Sheaf/EMB update: 16 November 2016
The work on Sheaf and EMB continues to progress really well ahead of next spring’s planned completion date. The majority of significantly disruptive, high risk works have been completed and towards the end of the year we will begin to move into final finishing and cosmetic works, although some periods of disturbance should still be … Continue reading Sheaf/EMB update: 16 November 2016
Sheaf/EMB update: 2 November 2016
Work has now begun on phase 4 of the STEM project, taking in areas of Sheaf Level 0 and EMB Level 0. This work, which will run until February 2017, will include breaking through between Sheaf and EMB to create a physical link between the two buildings, remodelling some classroom spaces, redefining escape routes and … Continue reading Sheaf/EMB update: 2 November 2016
Sheaf/EMB update: 19 October 2016
Work on phase 4 of the STEM project, taking in areas of Sheaf Level 0 and EMB Level 0, will begin on 31 October and run through until February 2017. This phase will include breaking through between Sheaf and EMB to create a physical link between the two buildings, remodelling some classroom spaces, redefining escape … Continue reading Sheaf/EMB update: 19 October 2016
Sheaf/EMB update: 5 October 2016
The work on Sheaf and EMB is progressing very well, with no majorly disruptive work planned for the next two weeks. Walls are being erected within the new atrium which will cause some noise but this won’t be too disruptive. There is an area of screed that will need to be removed close to the atrium … Continue reading Sheaf/EMB update: 5 October 2016
Sheaf/EMB update: 21 September 2016
Work on Sheaf and EMB continues to progress well as we head into the new academic year, with construction of the new atrium well underway. Erection of glazing on the roof lights began last week and the new stairways are currently being built. There is an area of screed around what was the old Sheaf/EMB … Continue reading Sheaf/EMB update: 21 September 2016