Work is continuing well in Sheaf and EMB with no major work to report. Refurbishment of Sheaf level 1 and EMB level 2 is ongoing and work on the new Atrium is also progressing, with decking installation begun last week. There is some drilling and breaking out work continuing over the next few weeks in … Continue reading Sheaf/EMB update: 13 July 2016
Sheaf/EMB update: 29 June
Instances of staff using the goods entrance and service yard to access Sheaf and EMB during the works has reduced in the last two weeks. Heavy vehicles and lifting equipment will continue to use this area for the foreseeable future, including delivery of steel for the atrium, so the contractor should be informed in advance of any … Continue reading Sheaf/EMB update: 29 June
Sheaf/EMB update: 15 June 2016
Anyone who has been in the vicinity of Sheaf and EMB – or indeed around Pond Street in general - in the last couple of weeks will have seen that the tower crane is now in situ and operational on the old NMB site. This will be up and running for several months as the … Continue reading Sheaf/EMB update: 15 June 2016
Sheaf/EMB update: 1 June 2016
The vast majority of the heavy demolition work planned for this phase of the project has been completed, and work over the next few weeks should cause very little disruption. The remaining areas of Sheaf level 2 were handed back to the University last week and these are being prepared for use. Initial strip-out and … Continue reading Sheaf/EMB update: 1 June 2016
Baroness Doreen Lawrence opens Charles Street
Baroness Doreen Lawrence OBE has officially opened our new £30million Charles Street Building - home of the Sheffield Institute of Education (SIoE). The new building houses more than 150 academic staff and 5,000 students, making it one of the largest providers of education training and research in the UK. The facility is part of a £100m … Continue reading Baroness Doreen Lawrence opens Charles Street
Sheaf/EMB update: 18 May 2016
Work on EMB level 2 is progressing to plan and computer installation for the handed-over areas has finished on this floor. Drainage works to level 1 and the catering unit are progressing well and expected to be complete by the end of this month. In order for the final section of the new drainage system … Continue reading Sheaf/EMB update: 18 May 2016
Sheaf/EMB update: 4 May 2106
Demolition and enabling works in the new Atrium, including breaking out work directly above 4027 and 4028, are nearly complete. Additional waterproofing may need to be added in these areas, and we did have two small issues with water ingress last week which were swiftly dealt with. Work in room 4027 itself has also finished, … Continue reading Sheaf/EMB update: 4 May 2106
Sheaf/EMB update: 20 April 2016
Work is continuing on EMB level 2, where flooring and ceiling decoration is progressing following the completion of demolition in that area. In the Atrium the temporary scaffold roof is currently being removed, steel work for the new lift shaft is being installed, and the new roof and gutter to Sheaf level 2 is almost … Continue reading Sheaf/EMB update: 20 April 2016
Sheaf/EMB update: 6 April 2016
We have now taken handover of the office areas of Sheaf level 2 following some additional work to parts of the ceiling. The remainder of this level, including the SCALE UP room and IT suite, will be handed back to us towards the end of April and fit-out work is continuing in these areas to … Continue reading Sheaf/EMB update: 6 April 2016
Sheaf/EMB update: 23 March 2016
Overall the STEM project continues to progress well and we are on track according to the current programme. We will take handover of the office areas of Sheaf level 2 next Thursday (31 Mar). Although this is around a week later than planned, there was always some flexibility in this date and we decided to … Continue reading Sheaf/EMB update: 23 March 2016