Work on the Sheaf and Eric Mensforth (EMB) buildings is progressing well. Level 3 of Sheaf is nearing completion. Ceiling and other installation work is being completed in the next couple of weeks, and new flooring is being laid and rooms prepared for redecoration. Our planned handover date for level 3 is 22 December and … Continue reading Sheaf/EMB update: 30 Nov 2015
Charles Street update: 23 November 2015
Since the last update we have been in constant communication with the contractors delivering the Charles Street build, Balfour Beatty, regarding progress on the project. Whilst there has been a significant improvement in performance over the previous few months, it is clear that a combination of the recent bad weather and the complexity around some … Continue reading Charles Street update: 23 November 2015
STEM update – 16 November 2015
Staff have now decanted from Sheaf level 2 and this has been handed over to the construction team to begin work this week. This means that work will now be taking place immediately above the level 1 helpdesk and the atrium. We are working with the contractors to minimise disruption to staff and students in … Continue reading STEM update – 16 November 2015
Charles Street update: 10/11/2015
The project has now achieved the critical milestone of the completion of the bridge creating the link from Charles Street to the Arundel building, including the cladding. The sustained effort and commitment from the contractor has clearly significantly progressed the building, with noticeable strides towards completion being made in all areas. We continue to closely monitor the progress on … Continue reading Charles Street update: 10/11/2015