Essential works will be undertaken to the electrical distribution board in the Harmer Building, level 1. During this time, the plantroom and adjacent areas will experience a power outage. The works begin on Saturday 3 and are expected to be complete by Sunday 4 August 2019. We apologise in advance for any inconvenience. If you … Continue reading Harmer Building, Level 1 Power Shutdown – Saturday 3 until Sunday 4 August
Owen Building, Level 12 Sensory Suite Refurbishment – Wednesday 31 July
In order to improve the student and staff experience the Sensory Suite on Owen level 12 will undergo refurbishment. During this period there will be noise disruptions, however we do not expect this to affect the surrounding areas. The works begin on Wednesday 31 July and are expected to be complete by Friday 30 August … Continue reading Owen Building, Level 12 Sensory Suite Refurbishment – Wednesday 31 July
City and Collegiate Campus, Glazing Works Programme
The next phase of the cross campus glazing works project begins on Monday 29 July and is expected to be complete by Thursday 22 August 2019. The work will take place on all levels on the internal doors, windows or side panels and will not cause any disruption to normal daily activities. If you have any queries, please contact … Continue reading City and Collegiate Campus, Glazing Works Programme
Surrey Building, Level 3 Architecture Studios Refurbishment
Starting this week, Architecture Studios 5306 and 5310 within the Surrey Building will be modernised as part of the Architecture Studios refurbishment project. The work commenced on Monday 22 July and is expected to be complete by Friday 13 September. There will be some noise disruption for the initial two weeks of the project which … Continue reading Surrey Building, Level 3 Architecture Studios Refurbishment
Harmer Building, Level 3 Carpeting Works
Next week, the Harmer Building Level 3 will have the carpets replaced within the walkways and circulation areas. The work is expected to begin on Monday 22 July and will take place out of normal working hours (6pm to 6am). This should take a week to complete and disruption should be minimal. If you have … Continue reading Harmer Building, Level 3 Carpeting Works
36 Collegiate Crescent, College House Tower Scaffold – Thursday 18 July
A tower scaffold will be erected on College House on Thursday 18 July to enable access to the roof in order to complete urgent works. This may cause a disruption to the access of the buildings rear car park. The works are expected to be complete by the following week. If you have any queries, please … Continue reading 36 Collegiate Crescent, College House Tower Scaffold – Thursday 18 July
Cantor Building Power Shutdown – Friday 16 August
In order to carry out essential maintenance to equipment on the University’s high voltage network, the Cantor Building will have a power shut down on Friday 16 August. Work will begin between 5pm - 6pm and is expected to be complete by midnight. We advise that no occupants can remain within the building during this … Continue reading Cantor Building Power Shutdown – Friday 16 August
Stoddart Glazing Works – Friday 12 until Tuesday 16 July
This Friday, the Stoddart building will be one of the first to have new safety film fitted to glazing areas as part of a cross campus glazing project. Work will take place on all levels on the internal doors, windows or side panels and will not cause any disruption to normal daily activities. The project … Continue reading Stoddart Glazing Works – Friday 12 until Tuesday 16 July
Road Closures in Sheffield – Sunday 14 July
We have been notified that some roads in Sheffield will be closed to traffic on Sunday 14 July for the HSBC UK Let's Ride event. This will affect routes to both Collegiate and City Campus. The following roads will be closed for the duration of the times stated: 7.30 am - 5pm Moore Street Charter … Continue reading Road Closures in Sheffield – Sunday 14 July
Road closures on Brown Street and Paternoster Row
Brown Street and Paternoster Row will be fully closed to traffic from Furnival Street to Surrey Lane from Saturday 27 to Sunday 28 July 2019, and Saturday 3 to Sunday 4 August 2019. This is due to road improvement works associated with the Knowledge Gateway. There will therefore be no parking or loading in this area for the … Continue reading Road closures on Brown Street and Paternoster Row