From Monday 17 August to Wednesday 30 September there will be excavation works in the Charles Street/Arundel Street junction which is planned to be done in 2 phases. Please see the traffic management plan for details on how traffic flow will be controlled in this area.

Phase 1 (approx. 2-3 weeks):

  • Setup traffic management
  • Excavation in junction
  • Pipeline tests and analysis of material requirements
  • Temporary back filling and reinstatement
  • Remove traffic management
  • Order materials

Interlude (approx. 2 weeks)

Phase 2 (approx. 3 weeks)

  • Setup traffic management
  • Excavation in junction
  • Repairs/replacement to pipeline under local DH network shutdown, which will also incorporate replacement of existing valves in alleyway adjacent Cantor Building
  • Back filling and reinstatement, including adjacent Cantor
  • Remove traffic management and replace footpath widening area

If you have any queries about the work, please contact Danny Crowther – Daniel.crowther@shu.ac.uk.