Part of the refurbishment works involves the upgrading of ceiling lighting throughout the floor. This is a roll out programme, with floor eleven being the first to be upgraded. This upgrade will run in conjunction with the refurbishment.
Each room on floor eleven will be affected by this upgrade. The contractors, NRC Services Limited will liaise with staff individually to agree a suitable time for the lighting to be installed within the staff offices. The instalment will be done out of office hours.
As part of the refurbishment and to comply with legislation, a new accessible toilet is to be installed between the male and female toilets. The toilets will be out of action; therefore the toilets on Level 10 will need to be used instead. Confirmation of dates for this work will be given closer to the time.
We’re sorry for any inconvenience this may cause. If you have any questions please contact Samantha Bowskill (Project Manager) on ext 3867.