We are currently carrying out an Electrical Fixed Wiring Inspection and Testing programme across the University Estate and the Sheaf Building and Owen Building levels 10, 9, 3, 2 are now due.
These tests are a requirement under the Electricity at Work Act which the University has to comply with.
The work involves a thorough inspection of the fixed wire installation and the carrying out of various tests as prescribed by the IEE Wiring Regulations and will involve interruptions to the power supply which we hope to keep to the absolute minimum. No interruptions will be carried out without prior arrangement and the contractor will be asked to carry out some tests out of normal working hours if required. Access will be required to all areas.
Please see proposed programme of works:-
Owen level 10 Week commencing 08/08/2017
Owen level 9 Week commencing 29/08/2017
Owen level 3 Week commencing 18/09/2017
Owen level 2 Week commencing 18/08/2017
Sheaf, week commencing 29/08/2017.