Refurbishment of Pennine Lecture Theatre

Throughout July, August and September refurbishment work will take place to the Pennine Lecture Theatre, associated WCs and PC Labs 5221, 5222 and 5223 on Level 2, Howard Building.

Work will begin on the PC Labs from Monday 7 July.  For two weeks from 7 – 21 July the Pennine Theatre and WCs will remain in use.  From Monday 21 July work will begin on The Pennine and WCs and the area will be out of bounds and blocked off from the atrium.

All works are due to be completed by w/c 22 September.