Automatic Metering Project

14 August

During August new meters are being installed to allow us to automatically monitor electricity, gas, water and heat in each building in real time which will help towards reducing our usage and overall carbon footprint.

To install the new meters shutdowns of services will be required and following consultation with key stakeholders in regards to the dates and times the schedule has been agreed as follows.  The shutdowns on the 26th and the 27th will be done during normal hours rather than overnight as the University is closed.

Please note that the Harmer electricity shutdown on the 27th has been scheduled to coincide with the power shutdown required for the current MERI refurbishment project on Harmer Level 0.  This will mean that Harmer will lose power and data, and Norfolk will lose data only on this date.

This information will also be available on the estates webpages and Future Spaces blog.

For any queries please contact Martyn Robinson on ext. 2715

Proposed shutdowns for Automatic Meter Reading Project:

Weds 14 August: Cantor (water)

Thurs 15 August: Collegiate Learning Centre (electricity); Surrey & Howard (water); Pearson (electricity).

Fri 16 August: Surrey & Howard (heat)

Sat 17 August: Surrey & Howard (heat)

Mon 19 August: Main building (Collegiate) (electricity)

Tues 20 August: Oaklands (electricity); The Lodge (electricity)

Weds 21 August: Adsetts (electricity); Stoddart (water)

Thurs 22 August: Eric Mensforth (electricity); Sheaf (electricity)

Fri 23 August: Adsetts (water)

Sat 24 August: Owen and Norfolk (water)

Mon 26 August: Eric Mensforth (heat); Surrey (electricity); Howard (electricity).

Tues 27 August: Norfolk (electricity); Harmer (electricity); Eric Mensforth (water).

Weds 28 August: HUBS (water)

Thurs 29 August: None proposed

Fri 30 August: Main building (Collegiate) (heat)

Sat 31 August: Main building (Collegiate) (heat)

Mon 2 September: None proposed

Tues 3 September: Collegiate Hall (electricity)