We will be carrying out essential roofing work to Willow Court (Collegiate Campus) from Wednesday 9th October. This is to replace the existing roof, which is currently leaking and impacting on teaching space. Once the work is complete, the new roof will resolve water ingress issues and improve the student experience.
The proposed dates for the project are all weather dependent and as such are subject to change. Any change to the proposed dates will be communicated further.
07th October to 14th October: Install scaffolding
14th October to 27th October: Main period of anticipated disruption to teaching spaces
28 October to 10th November: Completing all works, with minor disruption anticipated
11th November to 15th November: Dismantle Scaffold, minor disruption anticipated
If you have any queries about this work, please contact the Estates Project Manager; John McNamara on extension 2079 or by email at j.mcnamara@shu.ac.uk.