The next phase of the cross campus glazing works project begins on Monday 29 July and is expected to be complete by Thursday 22 August 2019. The work will take place on all levels on the internal doors, windows or side panels and will not cause any disruption to normal daily activities.
If you have any queries, please contact the Estates Apprentice Project Manager; Rebecca Johnson on Rebecca.Johnson@shu.ac.uk
City Campus Project Programme
Monday 29 July – Friday 2 August
Arundel Building
Monday 5 – Friday 9 August
Harmer, Norfolk, Surrey, Arundel Gate Court
Monday 12 – Friday 16 August
38-40 Howard Street, 42 Howard Street, 44 Howard Street, Charles Street Building, Bryan Nicholson Building, Matilda Street, Cleansing Depot, Workstation, SIA Post Office
Monday 19 – Tuesday 20 August
Eric Mensforth Building
Collegiate Campus Project Programme
Thursday 1 – Friday 2 August
Southbourne
Friday 2 – Monday 5 August
Mundella
Tuesday 6 – Wednesday 7 August
College House
Wednesday 7 August
The Lodge
Thursday 8 August
Collegiate Hall
Friday 9 August
Broomgrove Hall Teaching Block
Monday 12 August
Parkholme
Tuesday 13 August
Montgomery House
Wednesday 14 August
Mercury House
Thursday 15 August
The White House, Chestnut Court, Willow Court
Friday 16 August
The Mews, Robert Winston Building, Pearson Sports Hall
Tuesday 20 August
Oaklands, Main Hall
Wednesday 21 August
48 Collegiate Crescent, 51-53 Broomgrove Road
Thursday 22 August
Saunders, Club House