As part of the Estates long term maintenance plan we are looking to upgrade the existing electrical distribution within the Main Building at Collegiate Campus.
The main switchgear, from the records we have available serves the following buildings;
1. Main Hall
2. Pearson
3. 48 Collegiate Crescent (Gate House)
4. Collegiate Learning Centre (As an alternative – Adsetts will be open as usual)
5. Main Building Boiler house
In order for us to fully ascertain the requirements of the new switchgear we need to shut down power on the 8 June, from 6am to 3pm in the Main Building.
The above buildings will be without power for the duration of the shutdown and other areas may be affected.
Once we have gathered all the information we require then we can look to ordering the new switchgear.
The installation of the new switchgear is proposed to be carried out over 3 consecutive weekends, the Main Building switchgear is in 3 sections, we will look to replace one section per weekend.
The changeover works will take all weekend and during each changeover the affected buildings will be without power.
We would be looking to start at around 6pm on each Friday with completion on each Sunday.
If you have any queries, please contact the Estates Project Manager; Corinne Matthews on c.matthews@shu.ac.uk
If you would like to report a fault or maintenance issue, you can contact the Facilities Directorate Help Desk on 0114 225 4444 (Ext 4444), Monday to Friday 8am until 5pm.